Songa Enabler has commenced drilling of a new injection well for CO2 gas on the Snøhvit field off Hammerfest 29.juli.
Then start drilling of a production well that will provide replenishment of gas to Hammerfest LNG.
the fourth CAT D-rig came straight from the shipyard in South Korea and has started its first mission on the Norwegian shelf. It happens on Snøhvit to Statoil.
Must have new well
Snow White is still the only LNG project in the world where CO2 is separated from the well stream is captured and stored in a separate formation offshore.
so far saved more than four million tons of CO2 from the field, being watched so it does not interfere with the main reservoir as it is produced from. Now there is a need for a new CO2 injection well.
After the new CO2 injector is in place, the drilling rig directly over to drill the first new production well on snowy after the field started in 2007.
the drilling campaign is planned to last until Christmas.
– Important project for Statoil
in 2013, the project “CO2 solution project” established to build and install a new CO2 – injection well to replace the original injection well, which over time would leaked CO2 into gas reservoir at Snøhvit field, enter Statoil said in a statement.
– Hammerfest LNG need replenishing more gas to maintain high production and capacity utilization at the facility while we must ensure sustainable CO2 storage. Therefore, the project is important for Statoil, says Geir Owren, project manager for the project.
mid-2015 carried out a comprehensive marine campaign where pipelines and template for CO2 project was installed and linked to the existing subsea production facility on a snowy field.
the new subsea facility was built and installed undamaged and well within budget of 2.5 billion.
– the distance to the Barents Sea provides additional challenges in terms of mobilization and sailing, thus requiring careful planning, careful preparation and close collaboration with suppliers. We are satisfied with both equipment deliveries and marine operations, which resulted in a successful project, says project, Sveinung Øvretveit.
Now comes also Askeladd
the next major development step for Hammerfest LNG is the development of Askeladd field included in the plan for development and operation of Snøhvit license.
It is expected commencing in 2020/2021.
This development step will contribute to continued full capacity utilization at Hammerfest LNG.